Installing Electric Chain Hoist with Motorized Trolley




Please refer five items for installing electric chain hoist with a trolley. Before installation chain hoist attention regarding voltage. If the voltage is not proper, serious damage will occur to the working hoist. To prevent such an incident from happening to make sure that the wiring meets the requirements of a power supply.
  1. Attaching Chain Container
  2. Lubricating gear case
  3. Lubricating load chain
  4. Checking chain alignment
  5. Installing trolley and connecting it to the hoist

  • Attaching Chain Container
  • Attaching chain container

  • Lubricating Gear Case
  • lubricating gear case
    lubricating gear case
    There is no lubrication oil in the gear case during shipment. Unplug the oil plug, use pot nozzle to fill the gear case with gear oil and then put the oil plug back.

  • Lubricating Load Chain
  • lubrication
    lubrication
    Lubrication plays quite an important role in load chain service life. In order to extend the service life of load chain, please apply chain lubrication oil produced by a specific company or the one equal to lithium grease for industrial use. It is necessary to apply machine oil or gear oil on a regular basis.

Lubrication steps:

  • Plumb the no-load chain.
  • Clean offdust and water on the chain.
  • As shown in the diagram below, lubricate each link and load sheave or idle sheave.

  • Checking Chain Alignment


  • chain  alignment
    chain alignment

    Stock serial hoist with a load of capacity 3 tons or 5 tons has double chain fall model. Ensure not to overturn the bottom hook of double chain fall model. If it happens, reset it back to be normal. Make sure that welded part of chain keeps aligned. Do not suspend load on a twisted chain.

  • Installing trolley and connecting it to the hoist
  • (a) Equipping trolley

    • Insert suspension shaft into side plate G and lock it with suspension shaft bolt, slotted nut and split pin. 
      Ensure to fully bend both branches of split pin.
    • Insert fixing shaft into side plateGand lock it with split pin. Ensure to bend both branches of split pin.
    • As shown in table 5-2, load the suspension shaft with inner adjusting spacer.
    • Attach suspension shaft and fixing shaft to suspender T connecting with hoist body. Make sure that naine plates
      of hoist and trolley are in the same direction.
    • Attach more spacers on suspension shaft, and insert the suspension shaft and fixing shaft into side plate S.
    • Attach outer adjusting spacer and shaft stopper pin on the suspension shaft. Insert split pin into the shaft stopper pin. 
      Install shaft stopper and you can see split pin on the left side from the front oftrolley switch box when.

    (b) Adjusting trolley width

    Adjust trolley width
    • Adjust trolley width for proper space by referring to above picture. Size A is measured when two side plates are fully extended out.
    • Size A must be: about rail flange width (B) + 41n1n
    • To obtain above-stated size A, you should increase or decrease adjusting spacers, without taking into consideration numbers listed in table 5-2.
    • After size A is measured, insert the  split pin into shaft stopper pin. Ensure to bend the two branches of split pin.

    Comments

    1. Thank you so much for this nice information. Hope so many people will get aware of this and useful as well. And please keep update like this. Thank you so much for this nice information. Hope so many people will get aware of this and useful as well. And please keep update like this.

      ReplyDelete

    Post a Comment

    Popular posts from this blog

    Tips For Safe Crane Operation

    Crane operation , to be safe and efficient, needs talent, the exercise of utmost care and wisdom, alertness and concentration, and a rigid adherence to evidenced safety rules and practices as made public inapplicable and current ANSI and federal agency safety standards. Every crane operator, together with those concerned in throw masses and guiding lifting operations, should be trained and competent in each aspect of crane operations. There square measure four key points that workers should remember of in safe crane operation: How to arrange and manage lifting operations The development of safe procedures for operating with cranes How to supervise lifting operations properly Examining and reviewing operations and processes fastidiously What Safe Crane Operators have to be compelled to apprehend Although tower and mobile cranes square measure used extensively on  constructions come, they gift 3 vital dangers: Crane collapse – These incidents produce the tremendous p