Installing Electric Chain Hoist with Motorized Trolley

Please refer below five items for installing electric chain hoist with a trolley. Before installation chain hoist attention regarding voltage. If the voltage is not proper, serious damage will occur to the working hoist. To prevent such an incident from happening to make sure that the wiring meets the requirements of a power supply.
  1. Attaching Chain Container
  2. Lubricating gear case
  3. Lubricating load chain
  4. Checking chain alignment
  5. Installing the trolley and connecting it to the hoist

  • Lubricating Gear Case

There is no lubrication oil in the gear case during shipment. Unplug the oil plug, use pot nozzle to fill the gear case with gear oil and then put the oil plug back.

  • Lubricating Load Chain

Lubrication plays quite an important role in load chain service life. In order to extend the service life of the load chain, please apply chain lubrication oil produced by a specific company or the one equal to lithium grease for industrial use. It is necessary to apply machine oil or gear oil on a regular basis.

Lubrication steps:

  • Plumb the no-load chain.
  • Clean off dust and water on the chain.
  • As shown in the diagram below, lubricate each link and load sheave or idle sheave.

  • Checking Chain Alignment

chain alignment
Stock serial hoist with a load of the capacity of 3 tons or 5 tons has double chain fall model. Ensure not to overturn the bottom hook of the double chain fall model. If it happens, reset it back to be normal. Make sure that welded part of chain keeps aligned. Do not suspend load on a twisted chain.

  • Installing the trolley and connecting it to the hoist

(a) Equipping trolley

  • Insert suspension shaft into side plate G and lock it with suspension shaft bolt, slotted nut and split pin.
    Ensure to fully bend both branches of split pin.
  • Insert fixing shaft into side plate and lock it with a split pin. Ensure to bend both branches of split pin.
  • As shown in table 5-2, load the suspension shaft with inner adjusting spacer.
  • Attach suspension shaft and fixing shaft to suspender T connecting with hoist body. Make sure that nameplates
    of the hoist and trolley are in the same direction.
  • Attach more spacers on suspension shaft, and insert the suspension shaft and fixing shaft into side plate S.
  • Attach outer adjusting spacer and shaft stopper pin on the suspension shaft. Insert the split pin into the shaft stopper pin.
    Install shaft stopper and you can see the split pin on the left side from the front of the trolley switch box when.

(b) Adjusting trolley width

  • Adjust trolley width for proper space by referring to the above picture. Size A is measured when two side plates are fully extended out.
  • Size A must be: about rail flange width (B) + 41n1n
  • To obtain above-stated size A, you should increase or decrease adjusting spacers, without taking into consideration the numbers listed in table 5-2.
  • After size A is measured, insert a split pin into shaft stopper pin. Ensure to bend the two branches of split pin.

Comments

Popular posts from this blog

How To Install A Electric Chain Hoist?

Things to create positive before installation: The  electric chain hoist  and  trolley   are prepackaged severally. first, check if the number of the  hoist  accords with the number of units in the invoice and if their area unit any damages occurred from the transportation or abnormal packing. Also, Check the plate and see if the rated capacity, lifting speed, lifting height,  cross traveling   speed in addition because the power provide is up to plain. Check if screws of prime hook set are loosed and if the chains are knotted and twisted. 1. Check the track where the hoist and trolley combo is to be mounted: The run track of the hoist adopted is the I- Beam steel. The range of width is 75-180 mm for 1T - 2T and 100-180 mm for 3T-5T. The track for running should be smooth and its swerve radius cannot but the minimum radius stipulated within the plate. the location of axle height at the tip of the track should be mounted a physical property b...

#Industry #Cranes #Surat

For companies requiring overhead lifting operations, taking steps to avoid crane failure is critical to ensuring the safety of workers and overall efficiency of operations. No matter the specific  industry  or type of job site, taking a number of simple precautions can greatly reduce the risk of overhead crane failure. Employing high-quality, reliable  inspecting equipment  is critical for determining whether any mechanical problems are present that may lead to accidents. Inspections should involve checking for cracks, faulty wiring, worn-out ropes, and damaged parts. Crane technicians must also make sure the crane doesn’t exceed rated capacity and that all safety devices are working properly. Initial inspection — This consists of an inspection in accordance with the original manufacturer’s recommendations, as well as documentation of the inspection. Pre-shift inspection — This consists of an inspection in accordance with crane-operator. Frequent inspections ...